Cheptoris, Dev’t Partners Tour 240 Million Litre Per Day Katosi Water Treatment Plant

Cheptoris, Dev’t Partners Tour 240 Million Litre Per Day Katosi Water Treatment Plant

By Our Reporter
The Minister of Water and Environment Hon Sam Cheptoris, AFD Director General, French Ambassador to
Uganda H.E Jules-Armand Aniambossou, Germany Ambassador to Uganda H.E Mathias Schauer, NWSC Board Chairman Eng. Dr. Prof Badru. M. Kiggundu, NWSC MD Dr. Eng Silver Mugisha, Mukono South Area MP and members of the NWSC top management on Monday inspected the recently completed Katosi Water Treatment Plant.

Image

The plant, with a 240million litres per day water production capacity was constructed to add more water to the Kampala Metropolitan Service Area.

The project was jointly funded by Development Partners (EIB, AFD, KFW, EU-ITF), and counterpart funding from the Government of Uganda through the Ministry of Water and Environment and NWSC Katosi will serve over 7.5million people in Kampala, Mukono and Wakiso upto 2040.

Image

The plant has a design capacity of 160,000m³/day (80,000m3/day + 80,000m3/day), with provision for future expansion to 240,000m³/day. The Katosi-Kampala Transmission Mains on the other hand was designed to evacuate and convey all 160,000m3/day produced in Katosi into the Kampala Water supply network.

Main Project Components Katosi Drinking Water Treatment Plant;
•500m of DN1500 Off-shore Water Abstraction Pipeline into LakeVictoria (laid on the lake bed at a depth of 11m)
•Intake Structure and Raw Water Pump station on the shore of Lake Victoria
•Drinking Water Treatment Plant (DWTP) & Drinking Water Pumping Station (80,000m3/d + 80,000m3/d)
•Ductile Iron Pumping Transmission Main (10km, DN1400)
•Four (04) No. Storage Tanks at Nsumba hill, each with a capacity of 10,000m3
•33kV Power line extension from the new Mukono Industrial Estate Substation to the Katosi DWTP (over 40km)
•Administration Office Block, Laboratory, Workshop, Staff Houses
•Installation of SCADA and automation of the Plant operations

Katosi-Kampala Transmission Mains
•39km of DN 1400 ductile iron clear water transmission main from Nsumba reservoir to Namugongo
•2.3 km of DN 500/600 to existing reservoirs at Mukono and Seeta
•Reinforced concrete water storage reservoir of capacity 15,000 m3 at Sonde
•Booster station at Namugongo with two duty and one standby water pumps
•10 km of DN 700 ductile iron clear water pumping main, from Namugongo booster station to the existing Naguru reservoir.

•Staff houses at Sonde reservoir site and Namugongo booster station site.
•Installation of SCADA system.

The project also has a component to supply water to Katosi, Lugazi town and the surrounding areas.

Related post

KCCA boss inspects ongoing drainage projects along City’s major markets

KCCA boss inspects ongoing drainage projects along City’s major…

By Evans Najuna  Kampala – The Executive Director for Kampala Capital City Authority (KCCA) Ms. Dorothy Kisaka, on Monday conducted an…
Give priority to mental health – Deputy Speaker Thomas Tayebwa

Give priority to mental health – Deputy Speaker Thomas…

The Deputy Speaker of the Ugandan Parliament, Hon Thomas Tayebwa has said that mental health needs to be given priority in…
Uganda Hockey announce 36-Player Squad Men and Women for the Zambezi series

Uganda Hockey announce 36-Player Squad Men and Women for…

By Emmanuel Sekago Uganda Hockey has announced a 36-player squad, comprising both men and women, along with 14 reserves, for the…

Leave a Reply

Your email address will not be published. Required fields are marked *